15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

The Math Club is renting a banquet room for a party with door prizes. The banquet room costs $125 to reserve and the door prizes each cost $8.50. Find the possi
Evaluate the diagram below. Find the value of x and the measure of side EF.
Kam can make 72 cookies in 3 hours, Madison can make 128 cookies in 4 hours. How many hours would it take them to make 200 cookies together?
Tax collectors and messengers From the king all deserve their fate Humiliated in the town squares Burned and stuck in a mis’rable state What am I?
Evaluate [-1 -(-3) ] × (-4)​
Which equation could generate the curve in the graph below? On a coordinate plane, a parabola opens down. The parabola is in quadrants 2 and 3, and has its vert
what is the value of f (4) if it is defined by f (x) =2x+3
Which of the following is most likely the plot of a satire? A. A small dog, separated from her human family during a car trip, makes a long, dramatic journey ac
if river could speak prepare dialogue writing on the subject she talks among themselves​
i need to know the answer to this