a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

14/9 as a mixed number
in a basket, there are 24 good oranges and rest are bad oranges. The ratio of good oranges to the bad oranges is 3:1, find the number of bad oranges
"Find the length of AC for which ABCD is a parallelogram. A. 4 B. 6 C. 7 D. 8"
at the city museum child admission is $5.10 and adult admission is $9.60. on thursday 132 tickets were sold for a total sale of 898.20. how many child tickets w
Byetta ( generic name is exenatide) 5mcg BID within 60 minutes AC Bystolic ( generic name is nebivolol) 5mg po qd Ciprodex Otic (generic name is ciprofloxacin/d
how much cooler are sunspots than the sun
"1. Find the area of the regular polygon. Give the answer to the nearest tenth. pentagon with a side of 6 m (1 point) 123.9 m² 12.4 m² 61.9 m² 49.5 m"
What is the answer to 6-6-((-5)-7)
Review &reviewImagine that you have a bag containing 10 marbles ofdifferent colors. You have drawn a marble, recorded itscolor, and replaced it fifty times,
I don't get it !!?Which transformation will map figure H onto figure H'?A. Reflection across the y-axisB. Vertical translation of 10 unitsC. Vertical translatio